Dundas J.L. Grightmire Arena reaches partial occupancy

News Jun 03, 2019 by Craig Campbell Dundas Star News

City of Hamilton public works staff say the municipality took over part of J.L. Grightmire Arena from contractor Century Group at the end of April and removed most of the construction fence surrounding the Market Street construction site as the project finally achieved partial occupancy.

City spokesperson Jacqueline Durlov said the city and contractor are now working together to complete the long-delayed addition and renovation project. Completion is now nine months past the original Sept. 7, 2018, deadline.

“The contractor’s work will be complete on site by end of June, at which time the city will completely take over the site to finish up some minor works leading up to ice-making and fall 2019 hockey,” Durlov said.

Among the work still required is installation of a new flood-proof Zamboni door required by Hamilton Conservation Authority and new concrete stairs and wheelchair ramp in the area between the arena and Garstin Centre for the Arts building.

Durlov said the new flood-proof barriers arrived on-site several weeks ago and both key remaining jobs are scheduled to be completed by the end of June, but apparently aren’t required for occupancy and won’t delay reopening the arena.

Flood proofing the arena’s Zamboni entrance, either by raising the entire structure at considerable cost or finding a waterproof door, was a major early stumbling block to the original expansion and renovation application more than five years ago.

Peter Lloyd of Dundas Little Theatre said the organization has not heard when the new concrete steps and wheelchair ramp will be completed.

The group lost access to its main public entrance for the entire past season and part of the previous season.

“I seem to remember that the ramp has to be finished before we can open the (main) doors again,” Lloyd said.

The project tender stated that concrete stair and ramp work was to be completed by July 31, 2018.

The theatre’s 2019-2020 season is scheduled to open Oct. 25 with Einstein’s Gift. Lloyd said final receipts from the final show of the past season, Calendar Girls, have not been calculated yet so he wasn’t able to close the financial books on the difficult year.

“Fortunately, CG was a very popular show and we may recoup some of the shortfalls from earlier in the season,” Lloyd said. “But it was chaos some evenings trying to move a capacity crowd through the lobby without being able to open the main doors.”

The project tender also required the contractor to carefully remove, preserve and reinstall two commemorative stone plaques in the original façade, and an electronic outdoor sign.

Staff would not comment on the project’s deficit — which in December reached $228,680, or three per cent over the $7-million budget, or say if the contractor owes the city any money.

Durlov suggested those issues will be dealt with in a report to city council at a later date.

“We would like council and committee (to have) a genuine opportunity to review this information prior to it going out (to the public),” she said.

Durlov said the city’s recreation department will organize a grand reopening of the arena in the fall.

 

Dundas J.L. Grightmire Arena reaches partial occupancy

Flood-proof Zamboni door and outdoor concrete steps, ramp among remaining jobs

News Jun 03, 2019 by Craig Campbell Dundas Star News

City of Hamilton public works staff say the municipality took over part of J.L. Grightmire Arena from contractor Century Group at the end of April and removed most of the construction fence surrounding the Market Street construction site as the project finally achieved partial occupancy.

City spokesperson Jacqueline Durlov said the city and contractor are now working together to complete the long-delayed addition and renovation project. Completion is now nine months past the original Sept. 7, 2018, deadline.

“The contractor’s work will be complete on site by end of June, at which time the city will completely take over the site to finish up some minor works leading up to ice-making and fall 2019 hockey,” Durlov said.

Among the work still required is installation of a new flood-proof Zamboni door required by Hamilton Conservation Authority and new concrete stairs and wheelchair ramp in the area between the arena and Garstin Centre for the Arts building.

“The contractor’s work will be complete on site by end of June." — Jacqueline Durlov

Durlov said the new flood-proof barriers arrived on-site several weeks ago and both key remaining jobs are scheduled to be completed by the end of June, but apparently aren’t required for occupancy and won’t delay reopening the arena.

Flood proofing the arena’s Zamboni entrance, either by raising the entire structure at considerable cost or finding a waterproof door, was a major early stumbling block to the original expansion and renovation application more than five years ago.

Peter Lloyd of Dundas Little Theatre said the organization has not heard when the new concrete steps and wheelchair ramp will be completed.

The group lost access to its main public entrance for the entire past season and part of the previous season.

“I seem to remember that the ramp has to be finished before we can open the (main) doors again,” Lloyd said.

The project tender stated that concrete stair and ramp work was to be completed by July 31, 2018.

The theatre’s 2019-2020 season is scheduled to open Oct. 25 with Einstein’s Gift. Lloyd said final receipts from the final show of the past season, Calendar Girls, have not been calculated yet so he wasn’t able to close the financial books on the difficult year.

“Fortunately, CG was a very popular show and we may recoup some of the shortfalls from earlier in the season,” Lloyd said. “But it was chaos some evenings trying to move a capacity crowd through the lobby without being able to open the main doors.”

The project tender also required the contractor to carefully remove, preserve and reinstall two commemorative stone plaques in the original façade, and an electronic outdoor sign.

Staff would not comment on the project’s deficit — which in December reached $228,680, or three per cent over the $7-million budget, or say if the contractor owes the city any money.

Durlov suggested those issues will be dealt with in a report to city council at a later date.

“We would like council and committee (to have) a genuine opportunity to review this information prior to it going out (to the public),” she said.

Durlov said the city’s recreation department will organize a grand reopening of the arena in the fall.

 

Dundas J.L. Grightmire Arena reaches partial occupancy

Flood-proof Zamboni door and outdoor concrete steps, ramp among remaining jobs

News Jun 03, 2019 by Craig Campbell Dundas Star News

City of Hamilton public works staff say the municipality took over part of J.L. Grightmire Arena from contractor Century Group at the end of April and removed most of the construction fence surrounding the Market Street construction site as the project finally achieved partial occupancy.

City spokesperson Jacqueline Durlov said the city and contractor are now working together to complete the long-delayed addition and renovation project. Completion is now nine months past the original Sept. 7, 2018, deadline.

“The contractor’s work will be complete on site by end of June, at which time the city will completely take over the site to finish up some minor works leading up to ice-making and fall 2019 hockey,” Durlov said.

Among the work still required is installation of a new flood-proof Zamboni door required by Hamilton Conservation Authority and new concrete stairs and wheelchair ramp in the area between the arena and Garstin Centre for the Arts building.

“The contractor’s work will be complete on site by end of June." — Jacqueline Durlov

Durlov said the new flood-proof barriers arrived on-site several weeks ago and both key remaining jobs are scheduled to be completed by the end of June, but apparently aren’t required for occupancy and won’t delay reopening the arena.

Flood proofing the arena’s Zamboni entrance, either by raising the entire structure at considerable cost or finding a waterproof door, was a major early stumbling block to the original expansion and renovation application more than five years ago.

Peter Lloyd of Dundas Little Theatre said the organization has not heard when the new concrete steps and wheelchair ramp will be completed.

The group lost access to its main public entrance for the entire past season and part of the previous season.

“I seem to remember that the ramp has to be finished before we can open the (main) doors again,” Lloyd said.

The project tender stated that concrete stair and ramp work was to be completed by July 31, 2018.

The theatre’s 2019-2020 season is scheduled to open Oct. 25 with Einstein’s Gift. Lloyd said final receipts from the final show of the past season, Calendar Girls, have not been calculated yet so he wasn’t able to close the financial books on the difficult year.

“Fortunately, CG was a very popular show and we may recoup some of the shortfalls from earlier in the season,” Lloyd said. “But it was chaos some evenings trying to move a capacity crowd through the lobby without being able to open the main doors.”

The project tender also required the contractor to carefully remove, preserve and reinstall two commemorative stone plaques in the original façade, and an electronic outdoor sign.

Staff would not comment on the project’s deficit — which in December reached $228,680, or three per cent over the $7-million budget, or say if the contractor owes the city any money.

Durlov suggested those issues will be dealt with in a report to city council at a later date.

“We would like council and committee (to have) a genuine opportunity to review this information prior to it going out (to the public),” she said.

Durlov said the city’s recreation department will organize a grand reopening of the arena in the fall.